Construction site layout planning and safety management using fuzzy-based bee colony optimization model
- PDF / 2,212,631 Bytes
- 22 Pages / 595.276 x 790.866 pts Page_size
- 102 Downloads / 220 Views
(0123456789().,-volV)(0123456789(). ,- volV)
ORIGINAL ARTICLE
Construction site layout planning and safety management using fuzzybased bee colony optimization model Phong Thanh Nguyen1 Received: 24 April 2020 / Accepted: 9 September 2020 Springer-Verlag London Ltd., part of Springer Nature 2020
Abstract The construction site layout planning is an activity that establishes the temporary facility location, thereby enhancing the efficiency of the construction. Recently, safety enhancement plays a significant role in construction site layout planning. This paper aims in developing an optimal construction site layout planning by fulfilling three main objectives, namely minimum cost facility, minimum risk of safety facility and minimum noise pollution. In addition to this, this paper also proposes a fuzzy-based bee colony optimization (FBCO) algorithm for tuning q and s parameters so as to obtain a feasible and optimal solution. Also, this FBCO algorithm is employed to solve the construction site layout problem by satisfying the multi-objective function. Then, an FBCO-CLP approach is employed in obtaining a final optimal construction site layout plan. Moreover, the performance analysis of FBCO employs five benchmark functions to examine the effectiveness of the system for numerous aspects. Finally, a case study utilizes a residential building for verifying the proposed approach containing 13 temporary facilities. The experimental result reveals that the proposed FBCO-CSLP approach provides an optimal layout plan with minimum cost, noise pollution and safety risk facilities. Moreover, the comparative analysis is done by comparing the proposed approach with various other approaches such as ANN, GA, PSO, ABC and DE for three different types of facilities, namely cost facility, safety facility risk and noise facility. The experimental analysis reveals that the proposed approach provides better performances when compared with all other approaches. Keywords CSLP FBCO Cost facility Safety facility Noise pollution Temporary facilities Scenarios
1 Introduction At present, construction site layout planning turns out to be an effectual technique in promoting productive and secure operations that significantly reduces the movement of the equipment, travel time, obstructing as well as handling of the material [1]. Numerous research investigations and studies are performed under a dual-stage optimal site plan (i.e. under construction and pre-construction). Also, several soft computing techniques are developed in the recent years to estimate the desired construction site layout models [2] such as stability, permeability and material strength [3]. The pre-construction planning employs few & Phong Thanh Nguyen [email protected]; [email protected] 1
Department of Project Management, Faculty of Civil Engineering, Ho Chi Minh City Open University, Ho Chi Minh City, Vietnam
procedures, namely designing of a genetic algorithm, simulating and then formulating the mathematical model for construction [4]. Concurrent