Exploring Productivity of Concrete Truck for Multistory Building Projects Using Discrete Event Simulation

  • PDF / 646,236 Bytes
  • 15 Pages / 595 x 786 pts Page_size
  • 30 Downloads / 194 Views

DOWNLOAD

REPORT


pISSN 1226-7988, eISSN 1976-3808 www.springer.com/12205

DOI 10.1007/s12205-020-1389-z

Construction Management

Exploring Productivity of Concrete Truck for Multistory Building Projects Using Discrete Event Simulation Ha Duy Khanha and Soo-Yong Kimb a

Dept. of Civil Engineering, Ho Chi Minh City University of Technology and Education, Ho Chi Minh City 7000, Vietnam Member, Dept. of Civil Engineering, Pukyong National University, Busan 48513, Korea

b

ARTICLE HISTORY

ABSTRACT

Received 31 July 2019 Revised 1st 7 May 2020 Revised 2nd 9 June 2020 Accepted 27 July 2020 Published Online 9 October 2020

Concrete pouring activity is essential for the schedule and quality of the structural work construction. In practice, the process of concrete pouring is frequently congested and interrupted due to many unforeseeable reasons. The primary purpose of this study is to explore the productivity of concrete trucks for multistory building projects. The interview technique and work sampling method have been employed to collect the necessary data. Based on the literature review and experts' opinions, twenty-five factors affecting the productivity of pouring concrete have been found and discussed. Among them, there are seven factors identified as different from previous studies. Through two case studies of the hospital project, the actual average productivity of one concrete truck used to pour concrete into columns and walls is 0.184 m3/min by using a truck-mounted pump and 0.087 m3/min by using a tower crane. These productivities have been then determined based on discrete event simulation (DES). The simulation results indicated that the simulated productivity is higher than the actual productivity of approximately 16% and 13% for truck-mounted pump and tower crane, respectively. It is concluded that DES is a handy simulation tool for construction operations before the period of implementation. Based on the relationship between events of the process of concrete pouring, two relevant solutions have been proposed to enhance the productivity of concrete trucks. The results of this study may help practitioners manage the concreting activities in their projects with higher productivity.

KEYWORDS Productivity Concreting activity Discrete event simulation Construction management

1. Introduction Labor productivity is one of the most frequently studied areas in the construction industry because it is an important index to assess the efficiency of a construction project (Yi and Chan, 2014). In addition, Song and AbouRizk (2008), and Lee et al. (2017) concluded that labor productivity is also a necessary piece of information for predicting and planning a construction project. Moreover, Liu and Ballard (2008) indicated that labor productivity plays a crucial role in defining the project's financial success. It is due to labor productivity helps stakeholders to achieve the planned goals after completion. However, low productivity causes harmful impacts on project performance. Indeed, Doloi (2008) and Yang et al. (2014) demonstrated that p